Go to the homepage for the Sylva Herald and Ruralite

TWSA to proceed with Cashiers plant expansion

By Rose Hooper

Meeting at the same time Tuesday (Aug. 19), two separate Jackson County boards took action with regard to future development opportunities in Cashiers.

While the board of commissioners approved a commercial zoning district for Cashiers (see story page 1A), the Tuckaseigee Water and Sewer Authority gave its director, Hugh Montgomery, the go-ahead to proceed with engineering and permitting for an additional 100,000 gallons of wastewater treatment capacity at the Cashiers sewer plant.

Montgomery said he and Stan Bryson, TWSA's wastewater treatment plant superintendent, and Ben Henson, the plant's operator, have been working on a 90-day plan for increasing capacity at the Cashiers facility.

"Regardless of whether you approve our final plan or of what we do, we need a clarifier at that plant today," Montgomery told his board Tuesday.

Former TWSA Chairman Jerry King, who recently retired, estimated that cost to be around $200,000.

Although the state granted a permit in May 2002 for the Cashiers sewer plant to treat an additional 100,000 gallons of wastewater a day, the board chose to delay action until after the Cashiers incorporation vote, which failed Aug. 12.

Paige Bernstein, a supporter of incorporation, told the TWSA board that one reason he felt the effort didn't pass was "misinformation spread by those opposing incorporation." He then played a tape, recorded on his answering machine, alleging that if incorporation passed, the town would have to take over the costly operation of the treatment plant.

"We didn't have anything in the budget about taking over the plant," Bernstein said about what he termed a "scare tactic."

Lack of funds has also been a factor for TWSA, which placed a moratorium on the plant's expansion two years ago. Expansion was stalled initially when the $1,024,000 low bid for construction from RPB Systems Inc. of Asheville came in $224,000 higher than had been anticipated. In addition to the $1 million price tag for construction, Montgomery estimated another $300,000 would be needed for pump station upgrades, including auxiliary generators.

Collection system improvements have not been studied to include elimination of pump stations in exchange for installation of gravity lines, Montgomery said, estimating the cost of the analysis between $7,000 to $10,000.

Last year, several major developers, eager to access a portion of the additional 100,000 gallons, agreed to pay sewer impact fees totaling $950,000.

Back to Archive: 08/21/03.


Go to the Homepage Contact Subscribe Advertising Classifieds Archives Obituaries Submissions Deadlines About The Sylva Herald