Go to the homepage for the Sylva Herald and Ruralite

TWSA board to consider capacity, impacts on wastewater system

By Rose Hooper

Impact fees are hurting local businesses, said Western Builders owner Roger Bartlett, who urged Tuckaseigee Water and Sewer Authority board members to "give fair consideration to all who impact the system."

"I know (TWSA is) hurting for money, and I know you have to consider how developments impact your system," Bartlett told board members at Tuesday's meeting. "Those who build on an existing facility will impact the system the same as those who build on a new facility.

"Your heavy-hitters, your big users, don't even have to ante up," Bartlett continued. "If everyone were doing their part, paying their fair share, my impact fees wouldn't be so high. I ask you to treat every builder the same."

Bartlett calculated that to build a 3,300-square-foot office building serving 25 people on an acre and a half lot, he would have to pay $8,400 up front in fees before he could get any kind of permits.

Estimating 25 gallons per person, or 625 gallons per day, at TWSA's rate at $2.67 per gallon for water and $3.32 per gallon for wastewater, such a project would require $3,750 in impact fees, Bartlett said.

Impact fees are charges for a share of the cost of off-site improvements imposed on new connections.

Additionally, Bartlett said he would have to pay an acreage fee of $4,650. Acreage fees are designed to cover each tract's proportionate share of the cost of providing major trunk lines in the water and sewer systems.

"That's $8,400 before we put the first shovel in the ground. It's tough to put bids together when you have those kinds of fees upfront," Bartlett said.

It is also tough, he said, when the authority mandates that construction must be completed in six months.

TWSA Chairman Mickey Luker explained the time limit requirement was put in place so someone would not purchase allocations, then wait two or three years to build.

"I think you should give consideration for projects on an individual basis," Bartlett said. "Most take more than six months."

Agreeing with Bartlett, Steve Kenney of Bostic-Kenney Construction Co. said his company could not complete its proposed 500-bedroom apartment complex on Speedwell Road within six months.

"We can't build in six months; we are fast, but not that fast. We do plan to be open next July, in time for students next August," Kenney said.

Luker agreed the board will consider projects on an individual basis and that the time-frame issue will be taken up at the board's August meeting.

The board did take action Tuesday night by allocating 60,000 gallons per day of water and wastewater capacity for Kenney's apartment complex, which will overlook the Western Carolina University baseball field.

TWSA Executive Director Hugh Montgomery reported he had just completed an assessment of the authority's wastewater treatment capacity and determined some 300,000 gallons remained available.

A moratorium had been in effect until July 1 on new hookups exceeding 500 gallons per day, giving the new director time to complete his assessment.

The actual flow into the system is 1.2 million gallons per day, he said, with an additional 350,000 gpd when Western Carolina University students are on campus.

Another 136,570 gpd have been allocated to projects, for a total of 1,686,570 gpd. The permitted capacity is 2 million gpd.

"Roughly, that leaves us around 300,000 gpd," said Montgomery, or 240,000 after the allocation to Bostic-Kenney.

"That's if we operated at 100 percent capacity. But we have facilities that are 71 years old, and 100 percent efficiency every day is not possible given current staffing, tank age and process controls," Montgomery continued. "A more realistic goal is 80 to 85 percent of the design maximum. Thus, our 2 million gpd capacity would have best-case safe yield of 1.7 million gpd."

Montgomery added there was more to it than simply handling the flow.

"We have to treat those bio residuals to meet new stringent state requirements, and we have hydraulic restraints in our distribution system," he said.

Another dilemma TWSA faces, he said, are "the unknowns – large users coming on the system that we don't know about because they have historically not applied to TWSA for allocations."

Among those he listed were the new jail at the Justice Center, a new Social Services building planned in Webster, Harris Regional Hospital, WCU and Southwestern Community College. Public schools do not have to apply for or pay impact fees.

"I think Roger Bartlett is right; we need to look at how these large users impact our system, but pay no impact fees," said board member Jim Cochran.

That issue will also be considered at the board's Aug. 19 meeting.

Back to Archive: 07/17/03.


Go to the Homepage Contact Subscribe Advertising Classifieds Archives Obituaries Submissions Deadlines About The Sylva Herald