Go to the homepage for the Sylva Herald and Ruralite

Sylva officials approve additional funds for Moody Bottom sewer

By Carey King
and Lynn Hotaling


Sylva officials Aug. 15 approved an additional $55,000 for the ongoing Moody Bottom sewer project.
The vote was 4-1, with town board member Maurice Moody casting the "no" vote.

Project engineers Cavanaugh & Associates requested approval for a change order after poor soil quality on Allens Branch forced the contractor to haul in backfill.

Cavanaugh's Larry Barthelemy said his company found "blue clay" and large rocks all the way up Allens Branch. Clay is not suitable for backfill, and N.C. Department of Transportation specifications prevent replacing rocks larger than 4 inches in the ditch, Barthelemy said.

"Water will wash soil from between the rocks," he said. "At one point, the dirt was so bad and wet that the whole road almost gave way."

The original contract was based on backfilling the trench with the excavated soil; instead, contractors had to haul off the rocky soil and bring in stone backfill, Barthelemy said.

Cost of hauling away the original soil, plus bringing in and compacting the new backfill, was $30 per ton or $300 per load, Barthelemy said in response to a question from Moody.

Progress also slowed when the contractor discovered a Tuckaseigee Water and Sewer line on the left side of the road after being told the line was on the right, forcing them to shift work to the opposite side of the road, Barthelemy said.

Moody said he had no problem with the quality of the work completed but thought board members needed an itemized list of costs.

Moody also suggested board members postpone a decision on the additional funds until their September meeting, since the project completion date has been extended until Sept. 1.

Waiting would not be a problem, Barthelemy said, but he preferred approval beforehand.

"We're going to pay for it anyway," said board member Audrey Tritt, who seconded Eldridge Painter's motion to approve the change order.

Board members tabled the engineering firm's request for a $5,000 increase in administrative engineering fees.

Delays extending the project beyond its estimated length of three to four months resulted in additional supervision costs, Barthelemy said.

The contract estimated administrative costs at $20,000, not to exceed $28,000. Cavanaugh & Associates has requested an additional $5,000, bringing the total cost for construction oversight to $33,000.

"I don't think we should increase administrative costs," Moody said.\Moody's motion to deny the request failed for lack of a second.

Since Cavanaugh personnel did not do field work during rain delays, there is no justification for paying them additional money to supervise the project, Moody said.

Cavanaugh's Jason Robinson requested both change orders during the board's Aug. 7 session, but town board members postponed a decision until Aug. 15.

Sylva board members voted last fall to extend sewer access to the Moody Bottom area, which includes Allen Branch, Mitchell Road and Mills Branch. At that time, Barthelemy estimated the cost at some $534,000.

The project scope was extended May 1 to include a section of Scotts Creek Road after failing septic systems were identified in that area as well. Cavanaugh Associates estimated the cost of the Scotts Creek Road extension at about $85,000.

Back to Archive: 08/21/03.


Go to the Homepage Contact Subscribe Advertising Classifieds Archives Obituaries Submissions Deadlines About The Sylva Herald